Target Progress Tracker
31 March 2026 status quo and the journey to the 31 March 2027 (80%) target
174 days to 2027 target
31 March 2026 Status Quo
Achievement against the 65% milestone
53.85%achieved of 65% target
65%
Connected
11,781
65% Target
14,221
Shortfall
2,440
The national rollout finished 11.15 pp below the 31 March 2026 milestone.
31 March 2027 Target
Distance to the 80% goal
53.85%of 80% target (26.15 pp to go)
80%
Connected
11,781
80% Target
17,502
Sites to Go
5,721
Requires ~954 connections / month (~33 / day) over the remaining 6 months.
Current Progress
53.85%
2027 Target
0%
Gap to 80%
0 PSIs
Required Daily
0 PSIs
National Progress Tracker
53.8%connected
Current 53.8%
2026: 65%
2027: 80%
Milestone
31 Mar 2026
65% target · not met
Target
31 Mar 2027
80% target · 174 days
Gap to 2027 Target
Target PSIs (80%)17,502
Currently Connected11,781
Sites to Connect5,721 PSIs
Required Pace
Connect 954 PSIs / month (33 / day) to reach 80% by 31 March 2027.
Licensee Gap Analysis
Connected vs. sites still required to reach the 80% (2027) target
Vodacom
1,210 to go
Telkom
462 to go
Liquid
44 to go
MTN
1,956 to go
Rain
2,049 to go